Abstract:
In this paper, the arrangement of landslide monitoring points was introduced. According to the analysis of horizontal displacement and vertical displacement data before the anti-slide pile and after, the horizontal displacement rate of anti-slide pile is reduced from 0.65 mm/d to 0.03 mm/d, the vertical displacement rate is reduced from 0.05 mm/d to 0.01 mm/d. The horizontal displacement rate of the landslide area is reduced from 0.70 mm/d to 0.08 mm/d, the vertical displacement rate is reduced from 0.40 mm/d to 0.05 mm/d. Overall, the displacement of anti-slide pile tends to converge, the implementation effect is obvious, the landslide is stable. However, from the comparison of the landslide area and anti-slide pile area, there is still a possibility that the landslide is directly cut from the top of anti-slide pile, and it is still necessary to pay close attention to the landslide monitoring.
CLC Number:
P642.22|P228.4
WANG Jianying,HUANG Dewu. Analysis of Landslide Monitoring Results in Malutang Chengzi Resettlement[J]. JOURNAL OF KUNMING METALLURGY COLLEGE, 2016, 32(3): 31-35.
0 / / Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: http://kmyzxb.magtech.com.cn/EN/10. 3969/j. issn. 1009—0479.2016.03.006
http://kmyzxb.magtech.com.cn/EN/Y2016/V32/I3/31
[1]王庆宽,陈波,朱克.马鹿塘水电站移民安置点滑坡方案探讨[J].云南水力发电,2010,26(4):15-18. [2]DZ/T0219-2006,滑坡防治工程设计与施工技术规范[S]. [3]DZ/T0218-2006,滑坡防治工程勘查规范[S].